China Railway Seventh Group was awarded the tender at the beginning of this year and when the project commenced, at the beginning of 2013, it was estimated that it would be complete by October 2015.Principal Economic Planner Ethel Mosojane said this at the on-going full council meeting in Francistown when she was presenting the Urban Development Committee report. She said that the project that was supposed to be at 35 percent by now is only at 19 percent owing to a few factors.
She told the council that some things that could be contributing to the delay is the moving of water, power lines, telephone lines and also the relocation of 43 residents from Somerset East to Gerald who are supposed to make way for the development of the road. “As we speak bridges are being attended to and process of relocating the residents of Somerset East to Gerald Estates is also underway as they have been consulted and most of them have signed consent forms,” she said.She added that at the moment what is going on is the evaluation of their homes so that they can be compensated to go and build at their new homes in Gerald Estates. She added that there are a few residents with whom the council is still negotiating but most of them have complied.
Meanwhile she also talked about the Gerald Estates/Shashe Mooke Road that she said was seven percent ahead of schedule and the only issues were that there are plots along the road that had to be moved to make way for the development.”The good thing about this one is that the plots have not been developed yet so the compensation process is not so complicated,” she added.Another project that Mosojane said that was of concern is the Francistown stadium, which started in 2008.
The project stopped last at 93 percent and Mosojane said that the government is now looking to terminate the contract with the company that was awarded the tender to appoint a new company to complete the project.”To terminate the contract is also a long process but that is what is happening. Then a new company will be appointed to complete the stadium,” she said.Tuwana Construction left the stadium that was supposed to be complete ahead of the 2010 World Cup in South Africa, hanging and it has been that way since 2011.
Mosojane said that as the council they have also written a letter, whose response they have not yet received, to the ministry to find out what is going on with the stadium, which has become a thorn in the side of Francistown residents. In previous reports it had been stated that though the stadium was left at 93 percent the new contractor would probably have to demolish structures down to 65 percent because of poor workmanship by Tuwana Construction.